Transformers in Winter: Operating Checks and Maintenance Points Before the Cold Season
Transformers are built to run for decades, but winter asks a different set of questions than summer. Load curves change, oil behaves differently, and moisture that was harmless in warm months becomes a problem when temperatures drop. A short pre-winter inspection routine catches most cold-season faults before they turn into outages. Here is what to check, for both oil-immersed and dry-type units.
1. Oil level and oil behaviour (oil-immersed units)
Oil contracts as temperature falls. In autumn the level may look normal; by mid-winter it can sit below the minimum marking on the conservator gauge - and a low oil level exposes the core to air, accelerating insulation ageing. Check the level at the coldest part of the day, not at noon. If your unit will operate below −20 °C, confirm with the manufacturer that the oil grade suits low-temperature flow: cold oil becomes viscous, circulation slows, and cooling efficiency drops before the oil ever reaches the windings.
2. Breathers, gel and moisture control
The silica-gel breather is the most overlooked component in winter. Blue or orange gel that has already turned pale absorbs nothing - and in freezing conditions, a saturated breather plus warm humid daytime air means water condenses inside the tank on cold nights. Replace gel before winter, not after. Check that the oil cup under the breather has fluid but that it is not frozen; a frozen cup blocks breathing entirely.
3. Condensation and heater circuits (dry-type units)
Cast-resin dry-type transformers are often installed indoors, which sounds safe - but indoor temperature swings in unheated switch rooms produce exactly the condensation that anti-condensation heaters exist to prevent. Before winter: measure the heater circuit resistance, confirm thermostats switch on and off, and check that ventilation openings are not sealed shut against the cold. A dry-type unit running without its heater through a Central Asian winter is a scheduled insulation problem, not a random one.
4. Bushings and connections
Thermal cycling is harder on connections than steady cold. Every drop in temperature contracts metal slightly; over weeks of freeze–thaw, torque that was adequate in October can be loose in January. Inspection-style bushings and any removable links are worth a retorque and a thermal scan under load - hot spots almost always show up first at connections, and they show up worst in winter because the same cold that loosens metal also pushes load peaks to their annual maximum.
5. Load pattern and last thing first
Winter loading has two traps: evening peaks that run the unit above nameplate for hours, and long light-load nights that let moisture migrate into cooler insulation. If your network routinely exceeds rated output for hours on winter evenings, it is a transformer-selection question for the next expansion, not an operating trick.
When to call the factory, not just the local crew
Escalate to the manufacturer when: oil level keeps dropping after top-up (indicating a leak, not contraction), the gas relay operates even once, partial discharge or unusual hum appears with the cold, or SF6/pressure-type bushings show falling density gauges. These are not routine maintenance items - they need the test data and design margins on file.
Xunchi Electric supplies oil-immersed transformers of all common distribution and power ratings (including S11–S13 energy-saving series) and cast-resin dry-type transformers up to the 35 kV class, built to operate in the −30 °C to +40 °C ambient range with low-temperature options for special sites. If your project is in a cold-climate region, send us the site temperature record and we will specify the oil grade, heater configuration and breather design accordingly - through our website inquiry form or your usual export contact.